Sunday 27 May 2012

Mr B's painting marathon started with timber for the eaves.                                                         
                                                                     

Noah got to climb up the ladder to go "upstairs". Mrs B followed but didn't enjoy the experience as not very good with heights...             

Frame is up for downstairs, next some supporting walls upstairs and the roof trusses are being delivered and lifted up Monday week.


We have had amazing weather for the whole week, sunny and temperatures around +20 so couldn't ask for better conditions (plenty of sunscreen needed).

Tuesday 22 May 2012

Part II Begins

The concrete slab needed watering for couple days
so it wouldn't dry too quickly. Boys favorite job so far!  

First bits of timber frame went up on Monday

and here how the site looked Monday evening

Noah checking out the view from
his playroom window







Saturday 19 May 2012

Foundation on a plate


Here photo of the cake I made for our celebration for getting the foundation work done!

Thursday 17 May 2012

...and we have a beautiful concrete floor





Big load of timber arrived on site Wednesday morning so "the real building" can start. But before then we will celebrate getting the foundation done - part one is over!

Tuesday 15 May 2012

Underfloor heating...

...went in today so it's all systems go tomorrow for the concrete slab and also first load of timber is due to arrive on site! Mr. & Mrs. B had planned for a nice day off, shopping in Tampere, mummi looking after the boys.. and that's still the plan!





Monday 14 May 2012

Getting ready for casting the concrete slab...



So the foundation and ground work is nearly done, we are just waiting for the underfloor heating to be installed and then we are ready to cast the concrete slab! Once that is done (latest by next Monday) it's time for a little party, "valutalkoot" as we say in finnish. Mr B might have to open that nice bottle of Cognag he has stacked away and share it with the two hard working men, Ukki and Grandpa, who both have been slaving away non-stop since the beginning of the build.




Mr B and Ruben testing out the field behind the house for hockey, a welcome break from tying the iron bars! Ruben loves to drop by the building site after his morning in the day care. 




Wednesday 9 May 2012

It's starting to take shape!



Mr. B spent few hours plastering
the plinth(?) 




Downstairs toilet, kitchen/dining
area on the left, fireplace room
at the back left, livingroom at
the back.

Fireplace room

Sauna, shower room & utility room

Kids playroom

Hallway & porch

Sunday 6 May 2012

Latest developments


Very busy week behind, we finally moved to our temporary rental house and have spent the last few days making it our home for the time being. Lot has happened on the building front as well, here photos from the last week and latest ones from this morning.