Monday 10 September 2012

Six weeks late

The doors finally arrived this morning after being delayed for six weeks. They were lifted in their places except for the front door which will only be placed once the house is ready (we have an old door waiting to go in for the rest of the building time). Locks and handles were ordered today so hopefully soon we'll be able to lock the house (and move some stuff from our rental house in there as our utility room now is full of building supplies like the flooring materials, central hoover system, tiles, wall paper etc...) The roof "safety things" are installed and so are the drain pipes etc so good progress again. Now the site will be quiet until Friday as Ukki is taking a little break from it and goes to Estonia for a short Holiday. 






1 comment: