Tuesday, 2 October 2012

Insulation

Today the last bit of insulation went in. It was blown in under the roof, in the attic space between the inside ceiling and the roof, 80 m3 in total. So now we can really start heating up the house. Our HVAC guy and electrician have made long waited appearances on site and hopefully we will have the underfloor heating working soon. Also the last two missing door handles were installed yesterday and now we are just missing our plasterer who should come onboard any day now! The cladding is done and painted in the house, and some of the windows already have the surrounds. The car port cladding is nearly done as well and next jobs then are to finish the window surrounds and corner cladding for the house. Then we will move on to do the decking and main entry. 


No comments:

Post a Comment